Glattal progress
filed on:
05.07.2006 (5th Jul 2006)
A visit to the construction site of phase 1 of Glattalbahn today revealed that significant progress has been made since my previous visit (25th April). Track laying is no basically complete as far as the Ambassador junction and has also begun at the Auzelg terminus. Overhead masts are in position on all but a few short sections of the route but no catenary has been installed. The shelters at the stops are also taking shape.
For the latest photographs see today's new photo series (includes some Mulhouse shots from yesterday, a detour on my way home from work).
This news item is from the 2006 newslog.
search Zürich tram news archive news index for displayed year (2006)
news index for 2025
all news for current year Zürich tram homepage
to link to this item please use:
http://www.proaktiva.ch/tram/zurich/newslog/newsitem.php?year=2006&item=050706
|